[PDF]catcher bundle onshore precommissioning - Rackcdn.comhttps://993bc44c973f7d7ec2f5-9b3d1b7c7509f2288b53c72f3bba579f.ssl.cf3.rackcd...
11 downloads
147 Views
842KB Size
CASE STUDY Reference no. CS.PP.UKWA.012
PIPELINE & PROCESS
CATCHER BUNDLE ONSHORE PRECOMMISSIONING Country: Field: Year: Technologies:
UK Catcher 2016 - present Diesel pumps
Flushing units
Nitrogen convertor
Complete pre-commissioning of three bundles, including: Flowline flood and leak test, dewater and drying (87 pig runs) Control and chemical core flushed clean (200 km of tubing) Three bundles carriers packed with nitrogen in only three days (over 2.7 million scf injected) Towhead MEG injection and nitrogen packing
CHALLENGE As part of the wider Catcher contract in 2016, Altus Intervention was required to provide engineering, equipment and personnel in order to complete the full onshore pre-commissioning of three bundles (Catcher, Burgman and Varadero) on a tight, two-month schedule prior to launch.
SOLUTION An efficiently executed solution utilising dedicated teams and equipment to complete a significant number of operations within schedule completing the task with 16,600 personnel-hours and 19 wagonloads of equipment
RESULTS The completion of the pre-commissioning scope at Wester Site led to the launch of one of the operator’s most successful projects, with the delivery of three bundles to the Catcher field.
“…thank you to everyone who was involved in making the Catcher Project such a success at Wester Site. Our team efforts around very demanding phases of fabrication, test and launch was without doubt the main reasons we have delivered one of the best projects ever from site.”
For further information, please contact: www.altusintervention.com/expert