July 2015 Crossrail Farringdon Eastern Ticket Hall Bridge Link to Barbican Station Charterhouse and Carthusian Street westbound closure – August 2015 to August 2017 Thank you for your patience whilst we carry out the next phase of works to install the link bridge between the Barbican London Underground and Crossrail Farringdon stations.
Duration of work
Phase 3 – Basement foundation works in 33-37 Charterhouse Street
•
A work site compound will be erected outside 33-37 Charterhouse Street. This is to facilitate the necessary piling and construction works within the building to prepare for the bridge link between the stations. We apologise for any inconvenience but it will be necessary to close Charterhouse Square, Charterhouse Street and Carthusian Street to westbound traffic from Lindsey Street to Aldersgate Street. Eastbound traffic will not be affected. (Please see diagram overleaf) Three parking bays will be suspended to provide the one way carriageway in the eastbound direction. The zebra crossing by the school will remain operational.
Mid August to August 2017 including road closures • Week day working during core hours (08.00–18.00) • Possible extended hour working: Monday – Friday 08.00 – 19.00 Saturday - 09.00 – 16.00 Sunday – 09.00 – 16.00 • An element of 24/7 working
What to expect •
Phase 3 – Site set up at 33 – 37 Charterhouse Street •
Demolition of sections of the existing structure
•
Installation of piled foundations
•
Installation of temporary support structures
•
Excavation of material to lower existing basement
•
Installation of new floor slabs, lift structures and structural reinforcement
• •
What we will do •
• • • •
Platforms 2 & 3, Barbican Station
C435-XRL-Z-XBU-M123-50014
Suspension of three parking bays Some noisy periods from the breaking out and piling works Highlighted signage along diversion route Acoustic screening will be used to reduce the noise impact from the works Pedestrian access will be unaffected Noise and dust monitoring will be on going during the duration of the works Work areas will be securely fenced off Carry out a work safety audit
…continued from overleaf
Road Closure and Diversion Plan
We apologise in advance should this cause any disturbance. If you do have a complaint or query, please contact the Crossrail Helpdesk number listed below.
Works will be carried out in accordance to permission and consents granted by the respective Local Authorities. Once again, we apologise for any inconvenience and we thank you in advance for your patience. We will update you on planned works as the works progress
…continued from overleaf
About Crossrail Crossrail is Europe’s largest construction project, delivering a new railway for London and the South East. When the service opens Crossrail trains will travel from Reading and Heathrow in the west to Shenfield and Abbey Wood in the east via new twin tunnels under central London. It will link Heathrow Airport, the West End, the City of London and Canary Wharf.
Farringdon Community Liaison Panel Crossrail runs a community liaison panel for each central London station to keep local community representatives informed of progress and plans. If you would like further information please contact
[email protected]