[PDF]Flagler Avenue Sidewalk Study - River to Sea TPOhttps://www.r2ctpo.org/wp-content/uploads/Flagler-Av-Sidewalk-Study.pdfCachedderived from the GIS...
2 downloads
133 Views
33MB Size
Bicycle/Pedestrian Feasibility Study City of Edgewater Flagler Avenue Sidewalk
FINAL REPORT Prepared By:
Prepared For:
Reynolds, Smith and Hills, Inc.
Volusia TPO
January 2013
FINAL REPORT
Table of Contents INTRODUCTION........................................................................................................................... 1 PROJECT PURPOSE AND SCOPE ................................................................................................... 1 PHYSICAL INVENTORY AND ASSESSMENT OF RIGHT-OF-WAY ...................................................... 4 SIDEWALK CONCEPT PLAN ........................................................................................................ 12 FINANCIAL FEASIBILITY .............................................................................................................. 15 CONCLUSION ............................................................................................................................ 17 DATA COLLECTION REFERENCES ................................................................................................ 17 EXHIBITS ................................................................................................................................... 18
Tables and Figures Table 1 – Driveways Identified to be in Poor Condition ............................................................... 8 Table 2 – Existing Apparent Right-of-Way ................................................................................... 9 Table 3 – Quantities and Cost Estimate .................................................................................... 16 Figure 1 – Project Location Map ................................................................................................. 3 Figure 2 – Aerial View of School Entrance ................................................................................... 5 Figure 3 (Photograph) ................................................................................................................ 6 Figure 4 (Photograph) ................................................................................................................ 6 Figure 5 (Photograph) ................................................................................................................ 7 Figure 6 (Photograph) .............................................................................................................. 10 Figure 7 (Photograph) .............................................................................................................. 10 Figure 8 (Photograph) .............................................................................................................. 11 Figure 9 (Photograph) .............................................................................................................. 11
FINAL REPORT
i
Appendices Appendix A – Historical Plats ...................................................................................................A-1 Appendix B – Soil Survey Map .................................................................................................B-1 Appendix C – FDOT Right-of-way Forms and Confidence Ratings .............................................C-1 Appendix D – FDOT Inflation Factor Table ...............................................................................D-1
FINAL REPORT
ii
INTRODUCTION
In an effort to improve conditions within school walk zones, a Bicycle and Pedestrian School Safety Review Study for Edgewater Public Elementary School was prepared by Hoke Design, Inc. in November 2008, at the request of the Volusia Transportation Planning Organization (VTPO). Several sidewalk improvements were recommended as a result of the safety study. Of the recommendations, a proposed sidewalk along Flagler Avenue from Park Avenue to 12th Street was listed as the priority project. In addition to providing safer access to Edgewater Public Elementary School, the proposed sidewalk will provide local residents with safer access to public transportation, medical facilities, commercial properties, parks and recreation facilities, a cemetery, and the City of Edgewater municipal buildings.
PROJECT PURPOSE AND SCOPE
Edgewater Public Elementary School is located in a residential area in the City of Edgewater, Florida. There are few existing sidewalks located within the school’s designated walk zone. Flagler Avenue, from Park Avenue on the north end to 12th Street on the south end, is a main access road to the school. There is existing sidewalk along Park Avenue as well as 12th Street. Railroad tracks run between Flagler Avenue and the elementary school. Ocean Avenue, located between Park Avenue and 12th Street, crosses the railroad tracks providing direct access to the school. There is an existing sidewalk along the south side of Ocean Avenue which ends at the intersection with Flagler Avenue. The purpose of this study is to determine the feasibility of connecting these existing sidewalks by constructing a five-foot to six-foot wide sidewalk along Flagler Avenue, from Park Avenue to 12th Street. The proposed sidewalk is approximately 4800 feet long. This location was recommended the priority project in the 2008 Bicycle and Pedestrian School Safety Review Study for Edgewater Public Elementary School. Providing a continuous sidewalk along Flagler Avenue will not only benefit students, but will also improve safety for local residents walking or biking in the community.
FINAL REPORT
1
A cost estimate has been prepared as part of this study for Volusia TPO’s budgeting and planning purposes.
For the purposes of data collection, concept development, corridor
evaluation and cost estimation, a field review was conducted. The graphics within this report include notes, diagrams and callouts identifying the apparent right-of-way, driveways, existing sidewalks, and street names.
Considerations include
conformance to the requirements of the Americans with Disabilities Act (ADA), and appropriate signage and pavement markings along the facility at roadway and/or driveway crossings. This study required coordination with several agency representatives and stakeholders which the Study Team would like to thank for their continuing interest in this project and their assistance: Mr. Darren Lear – City of Edgewater Ms. Malecia Harris – City of Edgewater Ms. Saralee Morrissey – Volusia County Schools Ms. Tina Skipper – Volusia County Schools Mr. Stephan Harris – Volusia TPO Mr. Amir Asgarinik – FDOT
FINAL REPORT
2
Figure 1 – Project Location Map
Source: Parcel Data, Volusia County Property Appraiser
Source: Google Maps
Flagler Avenue Sidewalk Feasibility
PROJECT LOCATION MAP
FINAL REPORT
3
PHYSICAL INVENTORY AND ASSESSMENT OF RIGHT-OF-WAY
GENERAL DESCRIPTION The project corridor is located within the City of Edgewater, Florida. The proposed sidewalk is 0.91 miles in length, located along Flagler Avenue from Park Avenue to 12th Street. Park Avenue has an existing five-foot sidewalk on both sides of the road from US-1, continuing west beyond Flagler Avenue. Ocean Avenue intersects Flagler Avenue approximately 1600 feet south of Park Avenue. There is an existing sidewalk along the south side of Ocean Avenue beginning at Flagler Avenue and continuing east to US-1. There is an existing four-foot wide sidewalk along the south side of 12th Street, which terminates at the intersection with Flagler Avenue. Students walking or biking to school via Flagler Avenue to Ocean Avenue have to walk in the grass or on the road adjacent to vehicles. Constructing a sidewalk along Flagler Avenue was recommended as a priority project in the Bicycle and Pedestrian School Safety Review study report for Edgewater Public Elementary School which was prepared for the Volusia TPO in 2008. The study area traverses through a highly residential area. There are single family homes along both sides of Flagler Avenue as well as on all of the intersecting side streets. Florida Shores, a large residential development with more than 11,000 residents is located just to the south of the project limits. The study area is located within the designated walk-zone for Edgewater Public Elementary School, which is located east of the proposed sidewalk. The Bicycle and Pedestrian School Safety Review Study completed in 2008 estimated that during 2007/2008 school year, 90 of the 316 students residing in the walk zone, walked or rode bicycles to school. For the 2012/2013 school year, there are 570 students enrolled at the school, with 333 residing in the walk zone. The current number of students walking or biking to school is unavailable. The entrance to the school is located on Old County Road, east of the rail road tracks. Students living west of the railroad tracks access the school via Ocean Avenue. Figure 2 shows an aerial view of the school entrance.
FINAL REPORT
4
Figure 2 – Aerial View of School Entrance
Within a half-mile radius of the proposed sidewalk are several parks and recreation facilities, including a YMCA which provides after-school care to many of Edgewater Public Elementary School’s students. The existing sidewalks along Park Avenue and Ocean Avenue provide pedestrian access to medical facilities, a cemetery, the City of Edgewater City Hall and other municipal buildings, assisted living facilities, and many commercial properties located along US1. In addition, there are multiple Votran bus stops, which are part of the public transportation system in Volusia County, along US-1 located within ½ mile of the project corridor. A preliminary field review to develop the scope of the project was conducted by RS&H staff on October 18, 2012, and an additional field review was conducted by RS&H staff on December 4, 2012. During these reviews, existing land uses were noted, roadway crossings were assessed, underground and overhead utilities were inventoried, stormwater drainage features were identified, distance and offset measurements of various elements were conducted, and numerous photographs were taken.
FINAL REPORT
5
The Edgewater Public Elementary School Bicycle and Pedestrian School Safety Review Study recommended sidewalk along the east side of Flagler Avenue. After the preliminary field review, the corridor was analyzed using aerial imagery to evaluate if proposing the sidewalk along the west side of Flagler Avenue would provide any benefit. The school is located east of Flagler Avenue. Therefore if the sidewalk were constructed along the west side of the road, a crossing would be needed at some point in the corridor. Construction along the west side would only provide a benefit over the east if it could avoid a right-of-way acquisition. Based on the apparent right-of-way, an acquisition will be required regardless of which side the sidewalk is constructed. The cross drain located at the intersection of Flagler Avenue and 12th Street will require an extension on either side as well. Based on this assessment, it was determined that the east side of Flagler Avenue is the best location for the sidewalk. Therefore the east side was researched in more detail. The field reviews started from the northern end of the project where Flagler Avenue intersects with
Figure 3 – Facing North at the Intersection of Flagler Ave. and Park Ave.
Park Avenue (Figure 3). Traffic on Park Avenue is free flowing. Flagler Avenue is controlled by a stop sign. Flagler Avenue was measured to be 20 feet wide, with a posted speed limit of 25 MPH. All parcels along the project corridor were noted to be single family residential properties. Figure 4 – Existing Trees on Parcel 34-17-52-01-00-0405
Several trees were noted throughout the corridor on the east side of the road. Distances from the edge of pavement to the front of the trunks were generally measured to be 10 to 15 feet. However, the two trees located on Parcel 34-1752-01-00-0405, at the southeast corner of Park Avenue and Flagler Avenue (Figure 4) were located only eight feet from the edge of pavement.
FINAL REPORT
6
There are 41 residential driveways along the east side of Flagler Avenue.
Figure 5 – Facing North at the Intersection of Flagler Ave. and Park Ave.
They vary greatly in condition. Twentythree (23) of the paved driveways were found to be in poor condition with significant cracks or raveling of the asphalt or have no paved turnout at all. Figure 5 is an example of one of the existing driveways considered to be in poor condition. Dirt driveways and cracked driveways present a hazard to those traveling on a bicycle, in a wheel chair, or with a walker. These driveways have been summarized in Table 1. The remaining 18 driveways appeared to be in good condition with no noticeable cracks or deficiencies. However, in order to be ADA compliant, there must be a minimum four-foot wide area along the turnout profile that is no steeper than 2%. Many of the 18 driveways that are in good condition may be within the limits of ADA requirements. However, this cannot be verified without accurate survey information. Because it cannot be verified at this time, all driveways along the east side of Flagler Avenue are recommended to receive new ADA compliant concrete aprons.
FINAL REPORT
7
Table 1 - Driveways Identified to be in Poor Condition Reason for Proposing ADA Compliant Concrete Turnouts
Parcel ID
Address
34173202000070
303 S. Flagler Ave, Edgewater FL 32132
Poor condition
34173202000210
405 S. Flagler Ave, Edgewater FL 32132
34173202000260
308 W. Ocean Ave, Edgewater FL 32132
No turnout to tie into Exist. Driveway Dirt driveway ( Use as second driveway from Flagler Ave)
34173207000070
505 S. Flagler Ave, Edgewater FL 32132
No turnout to tie into Exist. Driveway
34173207000090
603 S. Flagler Ave, Edgewater FL 32132
No turnout to tie into Exist. Driveway
34173207000270
607 S. Flagler Ave, Edgewater FL 32132
No turnout to tie into Exist. Driveway
34173201000250
707 S. Flagler Ave, Edgewater FL 32132
Poor condition
34173201000260
801 S. Flagler Ave, Edgewater FL 32132
Poor condition
34173204000890
901 S. Flagler Ave, Edgewater FL 32132
Poor condition
34173204000940
905 S. Flagler Ave, Edgewater FL 32132
Poor condition
34173204000940
905 S. Flagler Ave, Edgewater FL 32132
Dirt driveway
34173204001020
915 S. Flagler Ave, Edgewater FL 32132
Dirt driveway
34173204001060
917 S. Flagler Ave, Edgewater FL 32132
Dirt driveway
34173204001120
925 S. Flagler Ave, Edgewater FL 32132
No turnout to tie into Exist. Driveway
34173206002500
927 S. Flagler Ave, Edgewater FL 32132
No turnout
34173206002490
929 S. Flagler Ave, Edgewater FL 32132
Poor condition
34173206002100
1003 S. Flagler Ave, Edgewater FL 32132
No turnout to tie into Exist. Driveway
34173206002090
1005 S. Flagler Ave, Edgewater FL 32132
No turnout
34173206002070
1009 S. Flagler Ave, Edgewater FL 32132
No turnout
34173206002070
1009 S. Flagler Ave, Edgewater FL 32132
No turnout (Dirt Driveway)
34173206002000
1021 S. Flagler Ave, Edgewater FL 32132
Dirt driveway
34173206001990
1027 S. Flagler Ave, Edgewater FL 32132
No turnout to tie into Exist. Driveway
34173206001950
1035 S. Flagler Ave, Edgewater FL 32132
Dirt driveway
FINAL REPORT
8
RIGHT-OF-WAY Flagler Avenue is a city street located in the City of Edgewater, Florida for which the City has maintenance responsibilities. Parcel lines obtained through the Volusia County Geographic Information Services (GIS), as well as plat maps provided by the City of Edgewater were used to assess the apparent right-of-way width. The plats provided label 50 feet of apparent right-ofway for Flagler Avenue from Beulah Avenue to the south. Joyce Street south to Alice Street and Adele Street south to Ann Street were also identified on the plats, however the width of Flagler Avenue right-of-way is not clearly defined. None of the plats contained enough information to accurately layout the apparent right-of way lines. These plats are included in Appendix A. Graphically, the parcels depicted on the historical plats appear to match the parcels obtained from GIS. As such, the GIS parcel lines were determined to be the best available estimate of apparent right-of-way for this study. Table 2 summarizes the apparent right-of-way information derived from the GIS parcel lines. Table 2 - Existing Apparent Right-of-Way Street
Approximate Linear Distance Flagler Ave. West Park Ave. to 820 ft. South of 820 ft. South Park Ave. (0.16 mi.) Flagler Ave. 195 ft. North of W. Adele St to 308 503 ft. ft. South of E. Ann St. (0.10 mi.) Flagler Ave. E. Ann St. to 283 ft. South of E. Ann 283 ft. St. (0.05 mi.) Flagler Ave. W. Ocean Ave. to 96 ft. South of W. 96 ft. Ocean Ave. (0.02 mi.) Flagler Ave. Joyce St. to 230 ft. North of Joyce 230 ft. St. (0.04 mi.) Flagler Ave. Joyce St. to 284 ft. South of Joyce 287 ft. St. (0.05 mi.) Flagler Ave. Joan St. to 213 ft. South-East of 213 ft. Joan St. (0.04 mi.) Flagler Ave. 57 ft. North of Jeanne St. to 236 ft. 293 ft. to Alice St. (0.06 mi.) Flagler Ave. 282 ft. between Alice St. and Linda 282 ft. St. (0.05 mi.) Flagler Ave. 358 ft. between Linda St. and Edith 358 ft. St. (0.07 mi.) Flagler Ave. 294 ft. between Edith St. and 294 ft. Beulah Dr. (0.05 mi.) Flagler Ave. 890 ft. South of Beulah Dr. to Lake 890 ft. Ave. (0.17 mi.) Flagler Ave. 269 ft. South of Lake Ave. to 12th 269 ft. St. (0.05 mi.) TOTAL DISTANCE 4818 ft. (0.91 mi.) Source: Volusia County Geographical Information Services Parcel Lines
FINAL REPORT
Location
Apparent R/W Width 54 ft. 56 ft. 54 ft. 62 ft 44 ft. Varies (38-53 ft.) 54 ft. 43 ft. Varies (47-50 ft.) Varies (47-50 ft.) Varies (43-51 ft.) Varies (54-52 ft.) 54 ft.
9
UTILITIES The utilities assessment was made
Figure 6 – Utility Box and Concrete Pad
through field visits. Overhead power lines are located along the entire corridor on both the east and west sides. The power poles located along the east side, where the sidewalk is proposed, are generally located eight to ten feet back from the edge of pavement. Adjacent to many of the power poles, were cable television utility boxes. There is a utility box and concrete pad located nine feet from the eastern edge of pavement on Flagler Avenue across from Jeanne Street, shown in Figure 6. It is recommended that the sidewalk meander closer to the road to avoid impacting this utility box.
Figure 7 – Power Pole and End Wall at Intersection of Flagler Ave. and 12th St.
There is a power pole on the east side of the project corridor located approximately eight feet from the existing cross drain end wall near 12th Street, shown in Figure 7. In order to construct a sidewalk as proposed in this study, the cross drain will need to be extended and a new end wall constructed. This drainage extension will potentially conflict with the existing power pole. As such, the power pole is recommended to be relocated approximately 16 feet to the north.
FINAL REPORT
10
There are several fire hydrants located along the east side of the corridor. The fire hydrants are
Figure 8 – Hydrant Located on the NE Corner of Flagler Ave. and Alice St.
generally located approximately 10 feet from the edge of pavement. At the intersection of Alice Street and Flagler Avenue, shown in Figure 8, the hydrant is only located eight feet from the edge of pavement. The sidewalk will need to shift closer to the road at this location in order to avoid the hydrant. There is a hydrant located at the southeast corner of Ocean Avenue and Flagler Avenue, just behind the existing sidewalk along Ocean Avenue. Based on the apparent right-of-way, and the location of the hydrant, it will need to be relocated in order to connect the proposed sidewalk along Flagler Avenue to the existing sidewalk along the south side of Ocean Avenue. DRAINAGE AND PERMITTING During the field assessment of the project corridor, no existing drainage systems were identified along the east side of Flagler Avenue between Park Avenue and the northern intersection with Beulah Drive. From Beulah Drive to 12th Street, there is an existing shallow swale located on the east side of the road. There are existing side drains located underneath the several of the driveways south of Beulah Drive, as well as a side drain beneath Beulah
Figure 9 – Existing End Wall at Northeast Corner of Flagler Avenue and 12th Street.
Drive at the southern intersection between Beulah Drive and Flagler Avenue. Just north of the intersection between Flagler Avenue and 12th Street there is an existing single pipe cross drain with sand-cement end walls. The end wall on the eastern side (Figure 9) of Flagler Avenue was measured to be approximately four-feet from the edge of travel lane.
FINAL REPORT
11
Based on the Volusia County GIS data, there are no wetlands in the area of the proposed sidewalk. While it is not anticipated, it is possible there could be small pockets of wetlands that are not picked up with the GIS data. Prior to surveying the job, a wetland assessment should be completed. If wetlands are found along the project, the Engineer of Record will need to coordinate with the U.S. Army Corps of Engineers during the design of this project to determine if a Dredge and Fill permit is required. In addition, an Environmental Resource Permit may be required from St. Johns River Water Management District if there are wetland impacts. If no wetlands are identified during the wetland assessment, the Engineer of Record should only need to obtain a Permit Exemption from St. Johns River Water Management District. SOILS INFORMATION The proposed sidewalk route traverses through Immokalee Sand and Myakka Fine Sand. Both are poorly drained sandy soils. A soil survey map is included in Appendix B. This map was prepared through the Web Soil Survey (WSS) operated by the USDA Natural Resources Conservation Service (NRCS).
SIDEWALK CONCEPT PLAN
The concept for this project is a four-inch concrete sidewalk, varying in width from five-feet to six-feet, located along the east side of Flagler Avenue from Park Avenue to 12th Street. The proposed sidewalk will begin at the southeast corner of the intersection between Park Avenue and Flagler Avenue and connect to the existing five-foot wide sidewalk running along the south side of Park Avenue. A six-foot wide sidewalk will continue in a southerly direction along the east side of Flagler Avenue offset five feet from the edge of pavement. The sidewalk shall maintain a minimum five-foot offset from the edge of pavement throughout the corridor except at isolated locations where the sidewalk meanders to avoid existing utilities, fire hydrants, or trees. When right-of-way allows, the sidewalk shall meander further from the road to be located behind the obstruction. For example, there are two trees located only eight feet from the edge of pavement on the north end of the project. In this location, there is approximately 23 feet of right-of-way on the east side of Flagler Avenue, which provides enough room to shift the six-foot wide sidewalk behind the trees. In cases where there is not enough right-of-way to construct
FINAL REPORT
12
sidewalk behind an obstruction, there are two options. The sidewalk can be shifted closer to the road for very short distances where the obstruction is located. The second option is to maintain the alignment of the sidewalk, but construct a reduced sidewalk width adjacent to the obstruction. For example, if the front of a power pole is located nine feet from the edge of pavement, the front edge of the sidewalk could be maintained at a five-foot offset from the edge of pavement, and the concrete would be cast around the pole providing an isolated width of four feet at the location of the pole. A minimum clear width of 36 inches is required by ADA standards. The Engineer of Record shall evaluate each obstruction during the design phase of this project to make a final determination on the alignment of the proposed sidewalk. New six-inch concrete aprons are proposed at all existing residential driveways (41 in total) throughout the project. Full topographical survey of the eastern driveways located within the right-of-way should be completed prior to design of the sidewalk. Several of the existing driveways appear to be in good condition with no noticeable cracks. If the survey shows that any of these driveways meet ADA requirements, the City and Engineer of Record may choose to leave the existing driveway in place, rather than construct a new apron. At each side street located along the east side of Flagler Avenue, where the sidewalk crosses, a standard crosswalk and stop bar is proposed. However, at Ocean Avenue, it is recommended that a special emphasis crosswalk be utilized since Ocean Avenue provides access across the railroad tracks and to the elementary school with higher pedestrian and vehicular traffic than the other side streets. The existing stop signs at all side streets shall be relocated to be in line with the proposed stop bar, a minimum of four feet behind the crosswalk. In addition to the stop signs, there are five additional single post signs along the east side of Flagler Avenue which will need to be relocated due to the construction of the sidewalk. Just south of Joyce Street, on the east side of Flagler Avenue and continuing to Joan Street, there is insufficient existing right-of-way available to construct the proposed sidewalk. There is also an inadequate amount of right-of-way along the west side of Flagler Avenue at the intersection with Joyce Street. Therefore, constructing the sidewalk along the west side of the road would not eliminate the need for a right-of-way acquisition. It is recommended that rightof-way be acquired from two single family residential parcels (parcel ID 34-17-32-07-00-0080 and parcel ID 34-17-32-07-00-0270), located along the east side of Flagler Avenue, shown on
FINAL REPORT
13
Exhibit 3. In order to minimize the square footage needed, the sidewalk alignment shifts to a two-foot offset from the edge of pavement just south of Joyce Street for approximately 50 feet. The right-of-way then allows for a four-foot offset from the edge of pavement for the next 100 feet, at which point the sidewalk again shifts to a two-foot offset from the edge of pavement. The sidewalk width from Joyce Street to Joan Street is also recommended to be reduced to five feet. Prior to design, the City of Edgewater will need to acquire right-of-way from these two identified parcels. Updated right-of-way maps should be developed by a Professional Surveyor and Mapper (PSM). Upon completion of the maps, the City can begin the acquisition process. The design and construction of this project is anticipated to be supplemented with federal funding, designating it as a Local Agency Program (LAP) project. The City of Edgewater will need to coordinate with the Florida Department of Transportation (FDOT) and fill out the LAP Rightof-way Acquisition form, which is included in Appendix C. In addition, Appendix C includes the District 5 Right-of-Way Cost Estimate Confidence Ratings information, the FDOT-approved Right of Entry Agreement form, and the FDOT-approved Donation of Property form, all of which may be useful to the City throughout the course of the project. The alignment shown in this concept report and described above is considered to be the minimum allowable design, requiring the least amount of additional right-of-way. If additional right-of-way can be acquired by the City of Edgewater, it is strongly recommended that the proposed sidewalk be located further from the edge of pavement. South of Joyce Street, the proposed sidewalk transitions back to the typical six-foot width located five feet from the edge of pavement. There are two existing palm trees that are in conflict with the proposed sidewalk (see Exhibit 4) which are recommended to be removed. The sidewalk is proposed to remain six feet wide to the intersection between Flagler Avenue and Linda Street. South of Linda Street to the end of the project, the apparent right-of-way line is located only 10.5 to 11 feet from the edge of pavement. In order to maintain a typical five-foot offset from the road, the sidewalk is proposed to continue south at a width of five feet. The existing shallow swale and existing side drains located at the southern end of the project will be impacted by the proposed sidewalk. The available right-of-way does not allow for a new swale to be graded between the road and the sidewalk. Therefore a back of sidewalk drainage system is proposed to replace the side drains and swale. The drainage pipes will flow to the
FINAL REPORT
14
south and connect to the existing cross drain located at 12th Street. The existing cross drain must be extended to accommodate a sidewalk. The existing end wall shall be removed and a new end wall constructed at the back of sidewalk. The existing power pole located directly west of the cross drain should be relocated to the north to allow for the construction of the new end wall. This relocation will need to be coordinated with the utility owner during the design phase. If the pole cannot be relocated, the sidewalk may be realigned to be closer to the edge of pavement, shortening the cross drain extension. However, traffic traveling east on 12th Street is heading directly toward the proposed sidewalk, before making a 90-degree turn to the north. In this particular location, the pedestrian traffic should be kept as far from the road as possible. The concept alignment and typical section that have been developed, and described above, are shown in Exhibits 1-7.
FINANCIAL FEASIBILITY Table 3 provides a preliminary cost estimate for the design and construction of the proposed sidewalk. This cost estimate is to be considered an opinion of probable cost based solely on the results of this feasibility study. The item numbers and units of measure are based on the Florida Department of Transportation (FDOT) Basis of Estimates Manual. The unit prices are based on historical average costs for each pay item as provided by FDOT. Some unit prices may have been inflated due to the small nature of the project. The cost estimate does not include right-of-way, utility relocation, tree removal, or permitting fees that may be associated with the final design phase. Based on the parcel lines obtained from the Volusia County GIS information, approximately one hundred eighty-eight (188) square feet of right-of-way will need to be acquired from Parcel 34-17-32-07-00-0080, located at the corner of Joyce Street and Flagler Avenue. One hundred sixty-nine (169) square feet will be needed from Parcel 34-17-32-07-000270, located at the corner of Joan Street and Flagler Avenue. The cost estimate for the proposed five-foot to six-foot wide sidewalk is $332,772. To adjust for potential future increases in the project's cost estimate, an annual inflationary factor may be applied. The Florida Department of Transportation provides annual inflation factors for roadway construction costs which may be used as a guideline for this sidewalk
FINAL REPORT
15
project. The 2013 cost estimate provided herein may be adjusted by the 3.3% FDOT inflationary factor for the next three years as follows: The inflation adjusted cost estimate for the Flagler Avenue Sidewalk for 2014, 2015, and 2016 is $343,753, $355,068, and $366,715, respectively. Table 3- Quantities and Cost Estimate
FINAL REPORT
16
CONCLUSION The purpose of this study was to evaluate the feasibility of constructing sidewalk along Flagler Avenue from Park Avenue to 12th Street. The proposed sidewalk is approximately 0.91 miles in length and is recommended to be located along the east side of the road. As a result of this study, it has been determined that constructing this sidewalk is feasible, with a couple of conditions. Right-of-way will need to be acquired from parcel 34-17-32-07-00-0080 and parcel 34-17-32-07-00-0270, both of which are single family residential properties. Prior to design and right-of-way acquisition, updated Right-of-Way Maps will need to be generated. Finally, the relocation of the power pole near 12th Street, due to the cross drain extension, and the relocation of the fire hydrant at Ocean Avenue, will need to be coordinated with the utility owners.
DATA COLLECTION REFERENCES Data collection sources used in the report included the following: • • • • • • • • • • • •
City of Edgewater, http://www.cityofedgewater.org/ City of Edgewater, Florida Submittal of XU Bicycle/Pedestrian Project application National Resources Conservation Service, Soil Survey of Volusia County (1980), http://soildatamart.nrcs.usda.gov/manuscripts/FL127/0/volusia.pdf http://www.city-data.com/ Volusia TPO, http://www.volusiatpo.org/ FDOT 2012 Basis of Estimates Manual Volusia County Property Appraiser’s Land Mapping System Edgewater Public Elementary School Bicycle and Pedestrian School Safety Review Study, Hoke Design, Inc. Google Maps, https://maps.google.com/ Volusia County Geographic Information Services (GIS) 2012 FDOT Volusia County Aerials, http://www.dot.state.fl.us/surveyingandmapping/ 2010 ADA Standards for Accessible Design
FINAL REPORT
17
LEGEND
LEGEND
HYDRANT
HYDRANT
P
UTILITY POLE
UTILITY POL
U
UTILITY BOX
UTILITY BOX
V
VALVE
A
ANTENNA
N
H
0
10
MAILBOX
VALVE ANTENNA
50
MAILBOX
Feet
EXIST. SIDEWALK TO REMAIN
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
START PROJECT
PROPOSED ADA COMPLIANT CONCRETE TURNOUT REPLACE EXIST. MAILBOX PROPOSED 6’ SIDEWALK APPARENT R/W LINE
REPLACE EXIST. MAILBOX
54’
P
FLAGLER AVENUE REPLACE EXIST. MAILBOX
EXIST. R/W
H P
P
P MEANDER SIDEWALK TO AVOID EXISTING TREES
PARK AVENUE
PROPOSED CROSSWALK AND STOP BAR
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
REPLACE EXIST. MAILBOX
18 REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
Reynolds, Smith and Hills, Inc. 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
SHEET
FLAGLER AVENUE SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT PLAN VOLUSIA CrawforN
2/21/2013
6:10:02 PM
EXHIBIT 1
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\PLAN
HYDRANT
P
UTILITY POLE
U
UTILITY BOX
V
VALVE
A
ANTENNA
ADELE STREE T
H
N
LEGEND
MAILBOX
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
0
10
50
Feet
LEGEND HYDRANT
UTILITY POL
PROPOSED 6’ SIDEWALK
UTILITY BOX VALVE
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
PROPOSED CROSSWALK AND STOP BAR
ANTENNA MAILBOX
PROPOSED 6’ SIDEWALK
EXIST. R/W
54’
APPARENT R/W LINE
P
P
PH
P
FLAGLER AVENUE REPLACE EXIST. MAILBOX
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
ADELE STREE T
ANN ST REET
REPLACE EXIST. MAILBOX
REPLACE EXIST. MAILBOX
19 REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
Reynolds, Smith and Hills, Inc. 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
SHEET
FLAGLER AVENUE SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT PLAN VOLUSIA CrawforN
2/21/2013
6:10:13 PM
EXHIBIT 2
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\PLAN
LEGEND
LEGEND
UTILITY BOX VALVE ANTENNA
APPARENT R/W LINE
REPLACE EXIST. MAILBOX
PROPOSED 6’ SIDEWALK
10
50
Feet
APPARENT R/W LINE
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
H
P
0
RELOCATE EXIST. FIRE HYDRANT
UTILITY BOX VALVE ANTENNA MAILBOX
P
P
FLAGLER AVENUE
EXIST. R/W
MAILBOX
54’
A
ANN ST REET
V
UTILITY POL EXIST. SIDEWALK TO REMAIN
JOYCE STREET
UTILITY POLE
U
N
P
HYDRANT
AVENUE
HYDRANT
W OCEA N
H
PROPOSED 6’ SIDEWALK
RELOCATE EXIST. SIGN
’ 4 4
PROPOSED CROSSWALK AND STOP BAR
. T IS X E
PROPOSED 6’ SIDEWALK TIE IN TO EXIST. SIDEWALK
/W R
PROPOSED R/W LINE APPARENT R/W
P
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
W OCEA N AVEN UE
PROPOSED SPECIAL EMPHASIS CROSSWALK AND STOP BAR
PROPOSED ADA COMPLIANT CONCRETE TURNOUT TIE IN TO EXISTING
EXIST. CONCRETE POST TO BE REMOVED
P
JOYCE STREET
PROPOSED CROSSWALK AND STOP BAR APPROX. 188 SF RW TO BE ADQUIRED FROM PARCEL ID #34-17-32-07-00-0080
PROPOSED 5’ SIDEWALK
REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
Reynolds, Smith and Hills, Inc. 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
20 SHEET
FLAGLER AVENUE SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT PLAN VOLUSIA CrawforN
2/21/2013
6:10:20 PM
EXHIBIT 3
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\PLAN
HYDRANT
P
UTILITY POLE
U
UTILITY BOX
V
VALVE
A
N
H
APPARENT R/W LINE REPLACE EXIST. MAILBOX
0
10
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
ANTENNA
ALI CE STR EET
LEGEND
50
Feet
MAILBOX PROPOSED 6’ SIDEWALK REPLACE EXIST. MAILBOX
JOAN S TREET
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
43’
P U
PROPOSED CROSSWALK AND STOP BAR
EXIST. R/W
APPARENT R/W LINE
P
HP
FLAGLER AVENUE
PROPOSED ADA COMPLIANT CONCRETE TURNOUT E 5 X 4 IS ’ T . R /W
PROPOSED 6’ SIDEWALK
PROPOSED 5’ SIDEWALK
PALM TREES TO BE REMOVED
APPARENT R/W LINE
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
ALI CE STR EET
PROPOSED R/W LINE
PROPOSED 6’ SIDEWALK
JEANNE STREET
APPARENT R/W LINE
PROPOSED CROSSWALK AND STOP BAR
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
APPROX. 169 SF RW TO BE ADQUIRED FROM PARCEL ID #34-17-32-07-00-0270
PROPOSED ADA COMPLIANT CONCRETE TURNOUT REPLACE EXIST. MAILBOX PROPOSED 5’ SIDEWALK
LAKE AVENUE 21
REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
Reynolds, Smith and Hills, Inc. 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
SHEET
FLAGLER AVENUE SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT PLAN VOLUSIA CrawforN
2/21/2013
6:10:27 PM
EXHIBIT 4
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\PLAN
LEGEND HYDRANT
P
UTILITY POLE
U
UTILITY BOX
V
VALVE
A
ANTENNA
N
H
0
10
MAILBOX
50
PROPOSED 6’ SIDEWALK
EDI TH STR EET
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
LI NDA ST REET
Feet
PROPOSED CROSSWALK AND STOP BAR
APPARENT R/W LINE
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
PROPOSED 5’ SIDEWALK PROPOSED 5’ SIDEWALK
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
APPARENT R/W LINE
P
P
P
FLAGLER AVENUE
EXIST. R/W
P
43’
50’
EXIST. R/W
P
P
P
PROPOSED CROSSWALK AND STOP BAR
RELOCATE EXIST. SIGN PROPOSED ADA COMPLIANT CONCRETE TURNOUT
REMOVED EXIST. SHRUBS TO ACCOMODATE PROPOSED 5’ SIDEWALK
RELOCATE EXIST. SIGN
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
22 REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
Reynolds, Smith and Hills, Inc. 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
SHEET
FLAGLER AVENUE SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT PLAN VOLUSIA CrawforN
2/21/2013
6:10:42 PM
EXHIBIT 5
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\PLAN
H
HYDRANT
P
UTILITY POLE
U
UTILITY BOX
V
VALVE
A
ANTENNA
N
LEGEND
0
10
MAILBOX
50
Feet
VE DRI LAH BEU
PROPOSED 5’ SIDEWALK
APPARENT R/W LINE
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
PROPOSED CROSSWALK AND STOP BAR
PROPOSED 5’ SIDEWALK
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
APPARENT R/W LINE
EXIST. R/W
54’
H
F L A GL E RA V E NUE EXIST. SIDE DRAINS TO BE REMOVED (TYPICAL)
REPLACE EXIST. MAILBOX PROPOSED ADA COMPLIANT CONCRETE TURNOUT
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
PROPOSED BACK OF SIDEWALK DRAINAGE SYSTEM
UE EN V A KE A L REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
Reynolds, Smith and Hills, Inc. 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
23 SHEET
FLAGLER AVENUE SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT PLAN VOLUSIA CrawforN
2/21/2013
6:10:56 PM
EXHIBIT 6
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\PLAN
HYDRANT
P
UTILITY POLE
U
UTILITY BOX
V
VALVE
A
ANTENNA
0
MAILBOX
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
PROPOSED 5’ SIDEWALK
PROPOSED ADA COMPLIANT CONCRETE TURNOUT
10
50
Feet
BEULAH DRI VE
H
N
LEGEND
APPARENT R/W LINE
END PROJECT RELOCATE EXIST. POWER POLE PROPOSED ENDWALL AND PIPE TO EXTEND CROSS DRAIN
APPARENT R/W LINE
PROPOSED 5’ SIDEWALK REPLACE EXIST. MAILBOX
P
A
F L A GL E RA V E NUE
EXIST. SIDE DRAINS TO BE REMOVED (TYPICAL)
EXIST. R/W
P
54’
EXIST. R/W
52’
H
PROPOSED MANHOLE RELOCATE EXIST. SIGN
PROPOSED CROSSWALK AND STOP BAR REPLACE EXIST. MAILBOX PROPOSED ADA COMPLIANT CONCRETE TURNOUT
UE EN V A KE A L
EXIST. SIDEWALK TO REMAIN
EXIST. R/W
68’
12TH STREET
PROPOSED BACK OF SIDEWALK DRAINAGE SYSTEM
24 REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
Reynolds, Smith and Hills, Inc. 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
SHEET
FLAGLER AVENUE SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT PLAN VOLUSIA CrawforN
2/21/2013
6:11:02 PM
EXHIBIT 7
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\PLAN
APPARENT R/W LINE
APPARENT R/W LINE
R/W VARIES 38’-62’
EXISTING EOP
SOD
VARIES 5’-6’
SOD VARIES 2’-5’
EXISTING EOP
10’
10’
VARIES 12’-23’
NATURAL GROUND
2 MAX. 0 . 0
NATURAL GROUND PROPOSED CONCRETE SIDEWALK
FLAGLER AVENUE TYPICAL SECTION PROPOSED SIDEWALK
25 REVISIONS
DATE
DESCRIPTION
DATE
STATE OF FLORIDA DESCRIPTION
DEPARTMENT OF TRANSPORTATION
. c n I , s l l dHi n ha t mi S , s d l o n y Re 1000 Legion Place, Suite 800 Orlando, Florida 32801 407-893-5800 FL Cert. No. EB0005620
ROAD NO.
COUNTY
SHEET
FLAGLER AVE. SIDEWALK
NO.
FINANCIAL PROJECT ID
CONCEPT TYPICAL SECTION VOLUSIA CrawforN
2/21/2013
6:11:12 PM
EXHIBIT 8
\\orlfile01\Transportation\P\1070936000_Volusia TPO Bike-Ped\Flagler Avenue\CADD\typs
APPENDIX A
A-1
APPENDIX B
B-1
80° 54' 13''
80° 54' 58''
Soil Map—Volusia County, Florida
508800
509000
509200
Edgewater Pa
lu ff
St
is Dr
y Wa
wo
ve
55
13
od e Av
St
3206400
wo
i on
St
A nn
e Av
d
Oc
St
ty R
A nn
47
an
Un
t le S
ou n
A de
ve ean A
Pl
1 £ ¤
St
e Oc
29
C Old
e
r Av
55
er
ton
t
ge
gl e
3206600
r St
yd
cS
Rid
Fla
de S ny
Sn
im a
S ut
e Av
4
rt A
Ot t
r er D
od
Ha
32
rr Me
3206600
lm
y Wa ge
Ave
Pa
lm
Rid
ad
3206800
ilr o
Av e
Pa
3206800
52
Ra
k P ar
28° 59' 28''
nc
eB
ay mW
Fra
Pin
l
3207000
508600
C
e onn
ct ic
ut A
Ch
ve
5
hS ur c
t Ho
te l
St 3206400
508400
3207000
508200 28° 59' 28''
5
e St Joyc
3206200
t ne S St
Lin da 3206000
17
37
St
Alice
St 3206000
Jean
St
29
ry Ma
3206200
Joan
29
55 ot A
ve
3205800
3205800
Tur g
Ma rilyn Ln
h St Edit
99 36 Lak
go
3205600
e Tr e
3205600
ve
Ruth Dr
eA
n Ma
36
Dr
55
Beulah Dr
12th St
80° 54' 58''
±
508400
508600
Marion Ave
508800
509000
Map Scale: 1:7,910 if printed on A size (8.5" x 11") sheet.
0 0
50
100 300
Natural Resources Conservation Service
200 600
Meters 300 1,200
3205400
t
Feet 1,800
Web Soil Survey National Cooperative Soil Survey
509200 80° 54' 13''
Dr
3205400
Tre e
508200
hS
Lime Tree Dr
Pin e
28° 58' 35''
14t
47
12/20/2012 Page 1 of 3
28° 58' 35''
Soil Map Units
Natural Resources Conservation Service
Stony Spot
Spoil Area
Sodic Spot
Slide or Slip
Sinkhole
Severely Eroded Spot
Sandy Spot
Saline Spot
Rock Outcrop
Perennial Water
Miscellaneous Water
Mine or Quarry
Marsh or swamp
Lava Flow
Landfill
Gravelly Spot
Gravel Pit
Closed Depression
Clay Spot
Borrow Pit
Blowout
Special Point Features
Soils
Area of Interest (AOI)
Area of Interest (AOI)
Other
Wet Spot
Very Stony Spot
Web Soil Survey National Cooperative Soil Survey
12/20/2012 Page 2 of 3
The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident.
Local Roads
11/5/2007
Date(s) aerial images were photographed:
Soil Survey Area: Volusia County, Florida Survey Area Data: Version 10, Sep 27, 2012
This product is generated from the USDA-NRCS certified data as of the version date(s) listed below.
Source of Map: Natural Resources Conservation Service Web Soil Survey URL: http://websoilsurvey.nrcs.usda.gov Coordinate System: UTM Zone 17N NAD83
Please rely on the bar scale on each map sheet for accurate map measurements.
Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale.
Warning: Soil Map may not be valid at this scale.
The soil surveys that comprise your AOI were mapped at 1:20,000.
Map Scale: 1:7,910 if printed on A size (8.5" × 11") sheet.
MAP INFORMATION
Major Roads
US Routes
Interstate Highways
Rails
Transportation
Streams and Canals
Water Features
Cities
Political Features
Other
Short Steep Slope
Gully
Special Line Features
MAP LEGEND
Soil Map–Volusia County, Florida
Soil Map–Volusia County, Florida
Map Unit Legend Volusia County, Florida (FL127) Map Unit Symbol
Map Unit Name
4
Astatula fine sand, 0 to 8 percent slopes
13
Cassia fine sand
17
Daytona sand, 0 to 5 percent slopes
29
Acres in AOI
Percent of AOI 23.4
7.9%
9.8
3.3%
38.8
13.1%
Immokalee sand
102.9
34.7%
32
Myakka fine sand
41.1
13.8%
36
Myakka variant fine sand
21.2
7.2%
37
Orsino fine sand, 0 to 5 percent slopes
6.5
2.2%
47
Pits
6.2
2.1%
52
Pompano fine sand
6.8
2.3%
55
Riviera fine sand
28.0
9.4%
99
Water
12.1
4.1%
296.8
100.0%
Totals for Area of Interest
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
12/20/2012 Page 3 of 3
APPENDIX C
C-1
District 5 Right of Way Cost Estimate Confidence Ratings: Introduction: The development of a right of way cost estimate is the product of four (4) essential components consisting of: (1) (2) (3) (4)
Quality and availability of the engineering or right of way exhibits. Quality and availability of market data. Time frame with which to develop the estimate. Ability and experience of the individual cost estimator.
The combination of these four essential elements serves as the foundation for the overall reliability of the right of way cost estimate. The following confidence levels represent a summation of these essential elements as they pertain to the development and reliability of an individual right of way cost estimate. A - High level of confidence – Usually prepared from 100% Right of Way Maps with excellent topography identified along with parcel sizes. Adequate sales and listing data are available. Adequate time is allowed to research available data and develop the estimate. B - Good level of confidence – Prepared from maps which have identified parcels and definite acquisition areas. Adequate sales and listing data are available. Adequate time is allowed to research available data and develop the estimate. C - Average level of confidence – Prepared from plans or maps which have identified parcels and definite acquisition areas. However, limited data and/or inadequate time required to analyze data typifies this confidence level. D - Fair level of confidence – Much of the needed data is lacking. Parcels may not be individually identified. A lack of project information as well as market data typifies this confidence level. Data lacking may include maps, sales, or adequate listing information. Time allowed to develop the estimate is not adequate to overcome these as well as other obstacles necessary to produce a more reliable estimate. E - Poor level of confidence – Plans or aerial maps usually lack any identified parcels and have only approximate R/W widths or take areas to work from. Market data and processing time are inadequate to produce a more reliable estimate. F - No confidence – None of the three elements consisting of plans/maps, market data, or adequate time necessary for the development of an accurate cost estimate are provided or available for consideration by the estimator.
C:\DOCUMENTS AND SETTINGS\CRAWFORN\LOCAL SETTINGS\TEMPORARY INTERNET FILES\CONTENT.OUTLOOK\P1PIMWUU\DISTRICT 5 RIGHT OF WAY COST ESTIMATE CONFIDENCE RATINGS (2).DOCX
5. If real property was donated, was the owner informed of his/her right to have an appraisal performed and a right to compensation? 6. Did the Agency provide any construction or regulatory elements in lieu of compensation that exceeded the value of the real estate?
4. Were good faith negotiations conducted with current appraisal values?
3. If answer to #2 is yes, were copies provided within 15 days of owner’s request?
2. Did property owner request copies of appraisal, maps or plans?
1. Were good faith negotiations carried out with representative after Representative Authorization (FDOT Form No. 575-030-02 or equivalent) was received? If property owner was not represented, write “N/A” in the comment section.
IV. Good Faith Negotiations
4. Was use of Appraisal Waiver properly executed? 5. If an uneconomic remnant was identified by the review appraiser, was an offer to purchase the uneconomic remnant made?
3. Was the offer amount based on recommended compensation?
1. Was Offer and Purchase Agreement (FDOT Form No. 575-030-07 or equivalent) delivered directly to the Property Owner? 2. Did we obtain a written acknowledgement of the Property Owner’s receipt of the Offer? If property owner refused to sign, note in comment section.
III. Offer(s)
5. Was a business damage claim paid?
1. Are there any businesses located on this parcel? 2. If answer to #1 is yes, was Notice to Business Owner (FDOT Form No. 575-030-033(34) or equivalent) delivered at or after I.N.? Date Delivered:___________________ 3. Based on the Secretary of State, Division of Corporations, was the registered agent notified? 4. Was the business eligible for business damages?
II. Business Owner Notification
1. Was Notice to Owner (FDOT Form No. 575-030-031(32) or equivalent) delivered at or before Negotiations? Date Delivered:. ____ . 2. Was the Notice sent to the owner’s last known address listed on the county ad valorem tax roll? 3. Was the Notice personally delivered or sent certified mail, return receipt requested? 4. Was ownership in the form of a representative capacity, i.e., corporation, partnership or trust? 5. If answer to #4 is yes, was Public Disclosure Notice (FDOT Form No. 575-030-18 or equivalent), delivered to the owner?
I. Property Owner Notification
Yes
Yes
Yes
Yes
No
No
No
No
N/A
N/A
N/A
N/A
Comments
Comments
Comments
Comments
Agency: _____________________ Project No.:_______________ Parcel No.:________ Consultant/Agent:___________________ Project Description:__________________________________________________________________________________________ FDOT Item/Segment No.:____________ FAP No.:____________ Owner:_____________________________ IN Date:___________ QA Review by:________________ QA Review Date:_________
Quality Assurance Review
Local Agency Program Right of Way Acquisition Worksheet
Date
Additional Comments:
1. Was the Right of Way Certification (FDOT Form No. 575-095-05 or equivalent) executed, accurate, and submitted to the Right of Way Office prior to letting? Date Certified :________________________
XI. LAP Certification
1. Was Request for Taxpayer ID (FDOT Form No. 575-030-27 or equivalent) delivered to non-excluded property owners? (Excluded = de minimis transactions and exempt transferors) 2. Was Form 1099S delivered to the property owner at closing or before December 31 of the calendar year in which the closing was held?.1099S Delivery Date: .
X. 1099S
2. Were fees and costs identified on the Purchase Agreement/Supplemental Agreement?
1. Were fees and costs based on an invoice or statutory formula? Method Used: ____________________
IX. Fees and Costs
1. Was Settlement Approval (FDOT Form No. 575-030-24 or equivalent) approved by the proper authority? 2. Was the settlement a justifiable expenditure based on settlement criteria?
VIII. Settlements
5. Was the Public Disclosure Affidavit returned at least 10 days prior to closing for ownerships in the form of a representative capacity, such as a corporation, partnership or trust?
4. Were all closing documents recorded no later than 48 hours after closing?
3. Were documents accurate and properly executed?
2. Did the closing take place within 60 days after Final Agency Acceptance?
1. Was Closing Statement (FDOT Form No. 575-030-16 or equivalent) prepared? . of Closing.
VII. Closing
4. Was Final Agency Acceptance granted at least 30 days after agreement was signed by both parties? FAA Date. .
3. Was Agreement reviewed by Legal?
2. Was Agreement inclusive of Fees & Costs?
1. Was an Agreement reached?
VI. Agreement
2. If applicable, was notice to business owner delivered prior to filing of suit? 3. Was the Public Disclosure Affidavit returned within 48 hours after OT deposit was made for ownerships in the form of a representative capacity such as a corporation, partnership or trust?
1. Did 30 days pass after offer was made before suit was filed?
V. Suit
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Comments
Comments
Comments
Comments
Comments
Comments
Comments
575-030-12 RIGHT OF WAY - 06/99
NOTE: THIS FORM SHOULD BE PRINTED ON OFFICIAL LETTERHEAD
Donation of Property to the County / or City USE THIS AREA FOR TYPING NAME & ADDRESS
ITEM/SEGMENT NO.: F.A.P. NO.: COUNTY / CITY ROAD NO. or PROPERTY ADDRESS: COUNTY/CITY: PARCEL NO.: INTEREST CONVEYED: This is to advise that the undersigned, as owner of the property or property interest referenced above and as shown on Right of Way maps for referenced project, desires to make a voluntary donation of said property or property interest to the County / City for the use and benefit of the County / City. The undersigned hereby acknowledges that he/she has been fully advised by a City / County representative of his/her right to have the referenced property or property interest appraised, to accompany the appraiser during the appraisal inspection of the property, to receive full compensation for the above referenced property, and to receive reimbursement for reasonable fees and costs incurred, if any. Having been fully informed of the above rights, I hereby waive those rights unless otherwise noted below.
Owner's Signature
Type or Print Property Owner's Name
Street Address
City, State, Zip Code
Date
RIGHT OF ENTRY AGREEMENT Financial Project ID: County Road: County: Parcel No.: STATE OF Florida COUNTY OF Seminole THIS AGREEMENT, made and entered into on the _____ day of _______________, 2009, by and between
Hereinafter called the “owner” and the State of Florida Department of Transportation, herein after called the ‘DEPARTMENT”. WITNESSETH: WHEREAS, the Department is conducting roadway improvements relative to the above referenced project; and NOW, THEREFORE, in consideration of the above stated premises, the Owner and the Department hereby agree that the Department and/or its duly authorized representative shall have the right to enter upon the Owner’s remaining lands for the purpose of performing demolition activities as noted below*. It is further understood and agreed that the Department and/or its duly authorized representative will restore the remaining lands to a safe and sanitary condition. *1. The contractor shall maintain access to 1311 Windsor Avenue during demolition in accordance with FDOT regulations. *2. The contractor shall contact the owner at 407/831-4053, prior to commencing any work on the owner’s property. *3. This right of entry is limited to demolishing the owner’s tennis court and accessory structures only (consisting of fencing, a light post, 10’clf, net/posts, water fountain, and concrete court itself) and re-seeding with grass. OWNER:
DEPARTMENT: STATE OF FLORIDA DEPARTMENT OF TRANSPORATION
By:____________________________ Signature Date
By:____________________________ Signature Date
_
_____________________________
_____________
Name (Please print or type)
Name (Please print or type)
APPENDIX D
D-1