May 7


[PDF]May 7 - Rackcdn.comd0a5726d3848a57dbf55-f9b6e4a1aac9d1d600e177fd0406dfb4.r4.cf2.rackcdn.com/...

15 downloads 120 Views 1MB Size

COMMONWEALTH OF MASSACHUSETTS DESIGNER SELECTION BOARD PROJECT CRITERIA DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

LAST DATE FOR FILING APPLICATION IS:

May 28, 2014

May 7, 2014 at 2:00 PM

The Board requests applications to be submitted by any of the following firms: ( (

X X

) )

Architect Architect/Engineer (A/E)

( (

) )

Engineer Other:

PROJECT NUMBER:

QCC1401 ST1

PROJECT TITLE:

QCC - New Classroom Building

PROJECT LOCATION:

Quinsigamond Community College, Worcester

AWARDING AGENCY:

Division of Capital Asset Management (DCAMM)

APPROPRIATION SOURCE:

Ch. 258 of 2008

AVAILABLE AMOUNT:

$15,931,331

ESTIMATED CONSTRUCTION COST:

$10,800,000

TOTAL FEE, excluding reimbursables or any authorized per diem payments, based on scope of work and services authorized if project is completed. ( (

X X

) )

Lump Sum Established Set Fee for Study Phase Per M.G.L. C.7C, §50 Lump Sum Established Set Fee for Final Design Phase Per M.G.L. C.7C, §50, based on the approved estimated construction cost in the certified study.

$200,000

dollars

7.2

percent

IMMEDIATE SERVICES AUTHORIZED: ( X ) CERTIFIABLE BUILDING STUDY ( ) OTHER: It is intended that the following continued services will be required of the selected Designer, and approval of the Designer by the DSB for the study phase shall also constitute approval of the Designer for continued services at the Awarding Authority’s discretion. If the Awarding Authority determines that the continued services will not be required of the Designer then the Awarding Authority must notify the Designer and the Board, upon making that determination. ( ( ( ( (

X X X X

) ) ) ) )

SCHEMATIC PLANS AND OUTLINE SPECIFICATIONS DESIGN DEVELOPMENT PLANS AND SPECIFICATIONS CONSTRUCTION PLANS AND SPECIFICATIONS ADMINISTRATION OF CONSTRUCTION CONTRACT OTHER:

MBE/WBE PARTICIPATION: In accordance with M.G.L. C.7C, §6 and Executive Orders 524 and 526, DCAMM has established a minimum combined MBE/WBE participation goal of 17.9% of the overall value of the study and final design contracts for this project. Applicants must utilize a mix of both MBE and WBE firms whose participation, when added together, meets the overall combined goal set for the Contract. The combined goal requires a reasonable representation of both MBE and WBE firm participation. The Combined MBE/WBE goal must be met within the list of requested prime and sub-consultants. All applicants must indicate in the prime firm’s application how they or their consultants will meet these goals and will be evaluated on that basis. Further information about the MBE/WBE Program appears in the DSB Public Notice at pages 4-8 titled “Participation by Minority Owned Businesses and Woman Owned Businesses,” in the Commonwealth of Study & Design Form Revised 10-12

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

Massachusetts Contract for Study Services (Revised 3/11) at Attachment C, in the Commonwealth of Massachusetts Contract for Final Design and Construction Administration Services (Revised 5/12) at Attachment E, and on the Supplier Diversity Office (formerly SOMWBA) website: http://www.mass.gov/sdo. Applications from MBE and WBE firms as prime consultant are encouraged. Applicants that are themselves MBE or WBE certified will be required to bring a reasonable amount of participation by a firm(s) that holds the certification which is not held by the applicant to the project. Proposed MBE/WBE participation plans that include solely MBE or solely WBE participation, or have only nominal participation by one or the other to meet the combined goal, will not be considered responsive. Applicants are strongly encouraged to utilize multiple disciplines and firms to meet the MBE/WBE goal. Consultants to the prime can team within their disciplines in order to meet the MBE/WBE goal, but must state this relationship on the organizational chart (Section 6 of the application form). APPROPRIATION LANGUAGE: Chapter 258 of 2008, Section 2, “. . . for additional classroom space at Quinsigamond Community College . . .” GENERAL SCOPE OF WORK: The selected Designer will prepare a certifiable study for the second of two phases of capital investment at Quinsigamond Community College (QCC) funded by the Higher Education Bond Bill of 2008. The first phase, a 35,800 GSF Science and Technology Building, is currently in design and expected to be occupied in the spring of 2016. The architectural program for the new building is anticipated to focus on increasing the College’s stock of instructional space. A preliminary program meeting the target construction budget will be proposed for evaluation in the study by an update to the 2006 Chan Krieger Master Plan performed by NBBJ and transmitted to the selected Designer prior to the initial project meeting. Key design objectives for the project include: State of the Art Design for College Instruction Instructional space provided by the project will be highly flexible, appropriately sized and equipped and incorporate the most current and best educational practices to maximize flexibility to address rapidly evolving instructional programs, technologies and approaches, including break-out, shared, and informal gathering space. Sustainable, High-performance Building and Landscape Design The design of the new Classroom Building will achieve the highest feasible energy efficiency and will consider geothermal, solar and other renewable energy sources. Civil and landscape design will emphasize water conservation, integrated storm water management, and low-maintenance ecologically appropriate planting design. Universal Architectural and Landscape Design The project will extend the College’s recent efforts to integrate architecture, site and landscape at QCC into a single, universally accessible design. Both the architectural and the landscape design of the project will provide internal and external pathways that avoid segregation of user groups and reliance on any of the “special” accommodations (furnishings, ramps, and signage) often encouraged by Code, and, wherever possible, exceed Code requirements.

DSB List#14-08 Item #1, Page 2 of 11

DSB LIST #

14-08

DSB List#14-08 Item #1, Page 3 of 11

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

Project Background Quinsigamond Community College (QCC) is located at 670 West Boylston St., Worcester, MA. It was established in 1963 to provide access to higher education to residents of Central Massachusetts. Since the early 60s, enrollment has grown from 300 to over 13,000 full and part-time day, weekend, and evening students served. QCC offers 70 associate degree and certificate career options in Business, Health Care, Technology, Liberal Arts, and Human Services. The College also offers a wide variety of non-credit courses, workshops, and seminars through its Division of Continuing Education at its downtown College at CitySquare campus. In addition, over 300 noncredit and nearly 150 credit courses are offered online. The College also has program locations at the Senior Center in Worcester (Hotel/Rest. Mgt.), Blackstone Valley Regional Technical High School in Upton (Automotive Technology), and at 5 Optical Drive on the grounds of the Southbridge Hotel and Conference Center. The College employs 850 full and part-time faculty, administration, and staff. In September 2014, QCC will open a state-of-the-art 72,409 SF Healthcare and Workforce Development Center at 18-20 Franklin Street in Worcester with space for an estimated 1,500 students. The facility will provide real-world medical facility settings equipped with video technology for five nursing programs and Radiologic Technology, Pharmacy Technician, Phlebotomy, Medical Assisting, and Surgical Technology programs. The College is accredited by the New England Association of Schools and Colleges (NEASC). Membership in the Association indicates that an institution has been stringently evaluated and found to meet high standards agreed upon by qualified educators. The Site Topography provides both distinctive physical character and unique development and circulation challenges at QCC. The fifty acre campus is on a hillside that rises 104 feet from the main entrance on West Boylston Street to the Burncoat Street entrance on the east in a series of terraces and “trays” that contain most of the College’s 1,558 surface parking spaces.

DSB List#14-08 Item #1, Page 4 of 11

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

Buildings and Classrooms All but two of QCC’s buildings were originally part of Assumption College, and were built, in a variety of materials and styles, between 1906 to the 1960s.

The Administration Building, looking east from West Boylston Street Alhfors Hall was added in 1992; in 2004 the 57,000 GSF Harrington Learning Center replaced the College’s old library in the North Wing of the Administration Building.

The Harrington Learning Center, looking north Today the buildings total 634,591 gross square feet, of which 380,786 is assignable, including 28,488 ASF of general classroom space and 20,520 ASF of specialized instructional space. Classrooms and other instructional spaces are primarily located in Surprenant (1965, 24,162 ASF) and the Administration Building (1906, 17,786 ASF), and in smaller numbers in Alhfors, the Athletic Center and the Harrington Learning Center. A Child Study Center is located adjacent to the main campus.

DSB List#14-08 Item #1, Page 5 of 11

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

The New Science and Technology Building A new 35,800 SF Science and Technology Building at QCC is currently in design and is expected to open in spring 2016. It will complement the Harrington Learning Center, frame a new interior landscape, and provide the first rungs of an architectural “ladder” up the slope from the Administration Building towards the student parking areas and the Athletic Center that will be completed by the new Classroom Building.

The architect’s rendering of the new Science and Technology Building, looking south with the Administration Building on the right. DETAILED SCOPE OF WORK Study Purpose The Designer will prepare a certifiable study that establishes the scope and estimated construction cost (ECC) of the project for final design as described in Study Phases below. Study Process The Designer is responsible for the development, documentation, coordinated analysis, and presentation of all data and products required to assist DCAMM and QCC in selecting the preferred option, to support pre-schematic design, and to develop an accurate ECC. Key conditions, issues, and options will be presented to DCAMM and QCC for discussion and review at a series of meetings scheduled at bi-weekly intervals throughout the study, recorded in the Designer’s meeting minutes, and documented in bound reports at the end of Phases 2 and 5. Study Phases Phases, tasks and deliverables for the study may be performed and delivered concurrently according the schedule developed by the Designer in Phase 1 (see Study Schedule, below). 1. Problem Definition and Schedule Participate in initial project meeting with the College working committee; develop project goals and problem statement and project schedule for College and DCAMM review and approval, including • A statement of the vision and goals for the project and the problems to be addressed • A draft study schedule for DCAMM review and approval (see Study Schedule, below)

DSB List#14-08 Item #1, Page 6 of 11

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

2.A. Existing Conditions Analysis The Existing Conditions phase will identify, document and analyze all existing building, site, campus and campus context conditions in detail sufficient to support the study design and an accurate cost estimate. All relevant information and data available from QCC and DCAMM will be delivered to the Designer prior to the initial project meeting. Additional surveys, borings and tests recommended by the Designer must be requested and authorized by DCAMM as extra services under the terms of the Study Contract. Deliverables will include all meetings and presentations required to fully present and analyze conditions which shall include, but not be limited to • The campus and its context and any area(s) recommended for further survey and geotechnical investigation • Location, capacity and condition of civil and utility systems available to the proposed site(s) • The most recent available design and construction documentation for the new Science and Technology Building • Adjacent site and buildings access conditions and issues • Energy Use Intensity (EUI) and water use goals analysis and recommendations 2.B. Program Analysis The Program Analysis phase will review and further refine the architectural program proposed by the NBBJ Master Plan Update and confirm a Preferred Program that • Meets all relevant DCAMM and industry space standards and utilization benchmarks • Includes an appropriate mix of space types and capacities • Can be built for the target construction budget confirmed by QCC and DCAMM. Deliverables will include all meetings and presentations required to present program options and confirm the Preferred Program and • A prioritized tabular analysis of existing, “right-sized” and future growth space proposed for the new building with appropriate departmental and building grossing factors • Detailed weekly utilization schedules for any proposed specialized (FICM 200) instructional spaces based on current Registrar’s data • A cost analysis meeting the requirements of the Consultants Estimating Manual for all program options considered • A Preferred Program table for College and DCAMM approval that includes all net spaces, with grossing factors • Draft room data sheets for all net spaces in the Preferred Program for DCAMM and QCC review 2.C. Existing Conditions and Program Report When Phases 2.A and 2.B have been completed and approved the Designer shall deliver • A draft Existing Conditions and Program Report documenting, narrating and graphically illustrating Phase 2 for DCAMM and QCC review, and • A final Existing Conditions and Program Report incorporating all revisions as directed by DCAMM for final DCAMM review and approval. 3. Options Analysis The Designer will develop and present a range of conceptual building and site design options for the Preferred Program meeting all access, energy and water use goals as required to confirm a preferred architectural, MEP, civil and site design approach for the project. Deliverables will include all meetings and presentations required to illustrate and evaluate options and costs and confirm the preferred solution. 4. Preferred Solution and Cost Estimate The Designer will prepare and deliver to the cost estimator a scope of design for the Preferred Solution that includes: • Dimensioned pre-schematic floor plans, elevations, sections, and blocking and stacking diagrams • A plan to scale showing building footprint and all proposed site, civil, and landscape work included in the estimate • Room data sheets for all net program spaces listed in the Tabular Architectural Program • Pricing narratives for all architectural, MEP, structural, civil, and landscape work • An outline specification • A schedule of design and construction

DSB List#14-08 Item #1, Page 7 of 11

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

The project cost estimator will prepare (1) a preliminary estimate based on the scope of design in Uniformat Level II format as required by DCAMM’s Consultants Estimating Manual for review. If the estimate is in excess of the budget target, the Designer will develop and recommend appropriate adjustments to the scope of design and, if necessary, the Preferred Program to reconcile the (2) final estimate to the target amount. 5. Final Report When Phases 3 – 4 have been completed and approved the Designer shall deliver • A draft Preferred Solution Report documenting Phases 3 – 4 for DCAMM and QCC review, and • A final Preferred Solution Report incorporating all revisions as directed by DCAMM for final DCAMM review and approval. Study Schedule The schedule prepared and approved in Phase 1 will assume DCAMM approval of the final version of the Preferred Solution report within six months of the initial project meeting and will include dates of delivery for all products and the dates, times, and agendas for all proposed project meetings. Activities shall be concurrent as required for efficient progress. The schedule will allow • Sufficient time for DCAMM to review and comment in advance on all meeting presentations, and • A minimum of two weeks for DCAMM and QCC to review and comment on draft and final reports.

ADDITIONAL SUPPORTING DOCUMENTS: The scope of work for this project is supported by the materials listed below, which are available for review and download on the Designer Selection Board website. •

BHE0502 ST1, Quinsigamond Community College: Space Utilization Analysis, Classrooms and Specialized Instructional Spaces, Rickes Associates, September 2006 http://www.mass.gov/anf/docs/dcam/dsblist/dsb140801-qcc-space-u-analysis.pdf



BHE0502 ST2, Master Planning for State and Community Colleges: Quinsigamond Community College, Chan Krieger Sieniewicz, August 2007 http://www.mass.gov/anf/docs/dcam/dsblist/dsb140801-mp-for-su-cc.pdf



QCC1001 ST1, Quinsigamond Community College: New Science and Technology Building, Consensus Solution Report http://www.mass.gov/anf/docs/dcam/dsblist/dsb140801-qcc-nstb-con-sol-rpt.pdf

GENERAL CONDITIONS OF THIS CONTRACT: Study Contract DCAMM has established a goal of six months to complete a study. If selected for study services, the applicant agrees to execute the Commonwealth of Massachusetts Contract for Study Services (Revised 3/11) (“Study Contract”) or its successor, without revisions or modifications. DCAMM compensates the designer during the Study Phase for approved products in accordance with the approved work plan. http://www.mass.gov/anf/docs/DCAMM/dlforms/forms/DCAMM-standard-study-contract.rtf Design Contract DCAMM has established a goal of twelve months to complete design (SD, DD and CD). At the conclusion of the study, if the applicant is requested by DCAMM to perform final design services, the applicant agrees to execute the Commonwealth of Massachusetts Contract for Final Design and Construction Administration Services (Revised 9/13) 1 (“Design Contract”) or its successor, without revisions or modifications. http://www.mass.gov/anf/docs/DCAMM/dlforms/forms/DCAMM-standard-design-contract.pdf

1

The Commonwealth of Massachusetts Contract for Final Design and Construction Administration Services (Revised 9/13) replaces the former DCAMM Form C-2 Contract for Designer Services. DSB List#14-08 Item #1, Page 8 of 11

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

SDVOBE Participation- Chapter 108 of the Acts of 2012; Executive Order 546 The Commonwealth encourages the participation of Service-Disabled Veteran-Owned Business Enterprises (“SDVOBE”) on its design projects. The benchmark for SDVOBE participation on DCAMM and other state agency design projects is 3% of the contract price as set forth in the standard DCAMM Study and Design Contracts referenced above. Financial Statement Chapter 7C, Section 51 requires that on public design contracts where the total design fee is expected to exceed $10,000 or for the design of a project for which the estimated construction cost is expected to exceed $100,000 the designer shall: a) File its latest CPA or PA audited financial statement with the Division of Capital Asset Management and Maintenance (DCAMM), and continue to do so annually throughout the term of the contract; b) Submit a statement from a CPA or PA that states that they have examined management’s internal auditing controls, and expresses their opinion regarding those controls. DCAMM Procedures The designer will follow the procedures established in DCAMM’s Designer Procedures Manual dated August 2008 (http://www.mass.gov/anf/docs/DCAMM/dlforms/designers-procedures-manual-aug08.pdf). Applicants are urged to review and become familiar with the following supplemental material, which is available on the web at: http://www.mass.gov/DCAMM. PMAS Consultants will be required to use DCAMM's electronic web-based Project Management and Accounting System (PMAS) as a repository for all project correspondence, documentation, and project budgeting, and scheduling. No special software is required. Workshops DCAMM and the Designer will hold periodic workshops to ensure that critical issues are not overlooked and that all team members have an opportunity to contribute their expertise, to anticipate potential obstacles, to identify potential solutions, and to expedite the decision-making process. Attendance by key design team members will be required at all workshops. Executive Order 484 This project shall comply with all applicable requirements of Executive Order 484 (EO 484): see http://www.mass.gov/governor/legislationeexecorder/executiveorder/executive-order-no-484.html. All building studies shall include preliminary estimates of the project’s energy use, water use, and greenhouse gas emissions using protocols established by EOEAA or as determined by DCAMM. No building study shall be certified for final design unless all means, methods, and commitments required to mitigate the project’s impact on the operating agency’s plan for meeting EO 484’s goals are documented in the consensus solution, implementation plan, and estimated construction cost. LEED Certification This project shall be certifiable at a level of Silver or higher, including Mass LEED Plus requirements. All measures proposed to achieve a LEED rating shall be incorporated into Final Design as part of the Designer’s base fee; administration of the certification process by the Designer during the Final Design and Construction phases of the project will be considered an extra service. Universal Design Design solutions provided under this contract are expected to provide an environment that meets the diverse and changing needs of users across age, ability, language, ethnicity and economic circumstance. DCAMM welcomes innovative design strategies that are usable by the widest range of people operating in the widest range of situations without special or separate design. Accessibility The consultant’s design must comply, at a minimum, with 521 CMR, The Rules and Regulations of the Architectural Access Board (http://www.mass.gov/eopss/consumer-prot-and-bus-lic/license-type/aab/aab-rules-and-regulations.html), as well as the 2010 ADA Standards for Accessible Design (http://www.ada.gov/regs2010/2010ADAStandards/2010ADAstandards.htm). When the requirements of these two laws differ the consultant shall comply with the one that provides the greater degree of accessibility. The consultant is also expected to understand and reflect in its design the civil rights obligations of the Commonwealth under Title II of the Americans with Disabilities Act (http://www.ada.gov/regs2010/titleII_2010/titleII_2010_regulations.htm) to provide equal DSB List#14-08 Item #1, Page 9 of 11

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

access to programs, services and activities. DCAMM may use its Accessibility Consultants to provide technical assistance and provide oversight for accessibility compliance during the design process. Environmental and other supplemental services DCAMM reserves the right to obtain supplemental services through independent consultants who will collaborate with the Principal-in-Charge (P.I.C.) and the project team. Construction Specifications The designer shall utilize the DCAMM Standard Specification. Cost Estimating Cost estimates, cost models, and estimator participation in both the study and the design phases shall meet the requirements of the current DCAMM Cost Estimating Manual and will be submitted in Uniformat II in the study phase and in both Uniformat II to Level 3 and CSI Masterformat in the design phase. The Cost Estimating Manual can be found at http://www.mass.gov/anf/docs/DCAMM/dlforms/cem-feb06.pdf, and Uniformat II can be found at http://fire.nist.gov/bfrlpubs/build99/PDF/b99080.pdf. Building Information Modeling (BIM) Building Information Modeling (BIM) will be used in the study, design, and construction phases of the project. The BIM List of Services can be found at http://www.mass.gov/anf/docs/dcam/dlforms/dcam-bim-list-of-services.pdf . This List of Services document is a general statement of DCAMM’s current requirements regarding the use of Building Information Modeling technology in agency projects. The specific requirements regarding use of the BIM will vary depending on the nature of the project, the Levels of Development delineated in the DCAMM approved BIM Execution Plan for the project, and the diverse purposes for which DCAMM will use the BIM during the life cycle of the facility from design through facility operations. In all instances, the language of the project contract(s) will be controlling. Building Commissioning DCAMM will include an independent third party building commissioning as part of this project. The Commissioning Agent will develop in collaboration with DCAMM an operations and maintenance plan as a reimbursable expense during the building commissioning phase. The commissioning agent will meet with DCAMM’s design team during planning, design and construction to evaluate design proposals and make recommendations to ensure the maintainability and operational efficiency of the new building. CM at Risk The construction of this project will be performed utilizing a construction management at-risk (CMAR, sometimes referred to as CM/GC) contract in accordance with MGL Chapter 149A. It is anticipated that the CM will be on board during the Schematic Design phase of Final Design project. Integrated Project Delivery Approach/Lean Construction Tools DCAMM may elect to use an Integrated Project Delivery (IPD) approach, as generally described in the AIA document Integrated Project Delivery: A Guide (2007) – (see http://info.aia.org/SiteObjects/files/IPD_Guide_2007.pdf for informational purposes). DCAMM's preliminary approach to IPD will use Construction Manager at Risk procurement with the goal that DCAMM, Client Agency, Designer, CM, Trade Partners, and other key stakeholders will work as an integrated project delivery team within the existing statutory and contractual frameworks. DCAMM may elect to use Lean Construction Tools as part of the IPD project delivery approach. The Lean Tools that DCAMM may use in connection with the project include Value Stream Mapping, Set Based Design, Target Value Design, A3 Decision-making, and Last Planner™ - (see http://www.leanconstruction.org/pdf/6_Lichtig_Howell_LCI_Glossary.pdf for informational purposes). CONDITIONS FOR APPLICATION: Current or updated Master File Brochures must be on file with the Board. As a condition of application, each applicant, if selected for the new project, agrees to carry professional liability insurance in an amount equal to the lesser of $5,000,000 or 10% of the Project’s Fixed Limit Construction Cost, but in no event less than $250,000 per claim in accordance with the Study Contract and Design Contract (i.e., minimum coverage of $250,000 up to $5,000,000 depending on the construction cost). DCAMM may seek additional coverage for the selected designer, and if so will bear the cost of the additional coverage. Note that the requirement for professional liability insurance shall apply to both the Contract for Study Services DSB List#14-08 Item #1, Page 10 of 11

DSB LIST #

14-08

ITEM #

1

DSB PUBLIC NOTICE DATE:

May 7, 2014

and Contract for Final Design and Construction Administrative Services when a project is advertised for both study and design services. APPLICATION EVALUATION – PERSONNEL Applications will be evaluated based on the applicant and consultant’s personnel and extent of compliance with MBE/WBE participation goals. Please see Section 6 on DSB Application Form: On the organizational chart, identify the team by listing them in the same order as below. Include resumes for all personnel. 1. 2. 3. 4.

Architect (P.I.C.)* Mechanical Engineer (M/P/FP) Electrical Engineer Structural Engineer

5.

Civil Engineer

6. 7. 8. 9.

Landscape Architect Specifications Consultant (independent consultant required) Cost Estimator (independent consultant required) MA Building Code Consultant (independent consultant required)

*Should the advertisement require the applicant to be either an Architect or an A&E firm, the P.I.C. or P.M. must be a Registered Architect in the Commonwealth of Massachusetts. Where an “independent consultant” is required the Applicant may not provide the services “in house.” If the Applicant plans to fulfill any of the other sub-consultant roles, so indicate on the organizational chart. Project Managers for Study and Final Design should be listed separately on the organizational chart. APPLICATION EVALUATION – PROJECT EXPERIENCE Applications will be evaluated based upon the requirements of M.G.L. Ch. 7C §49 and the work listed on DSB Application Form Sections 8, 9 AND 10 which illustrate current qualifications in the following areas: 1.

Architect: planning, programming, design and construction of instructional space for Community Colleges.

3.

Architect and Landscape Architect: design and construction of universally accessible buildings and landscapes.

2.

Architect and M/E/P Engineers: design and construction of high-performance buildings of comparable region, size and type; previous experience as team preferred.

4.

Landscape Architect: landscape design based on ecological analysis.

APPLICANTS PLEASE NOTE A copy of the most current Application Form and General Instructions - DSB Application Form (Updated February 2013) are included with this Public Notice and available for download at www.mass.gov/dcam/dsb Applications that are incomplete will be rejected. Applications that are submitted on a form other than DSB Application Form (Updated February 2013) may be rejected as non-compliant and not be considered by the Board. Applications received at the DSB Office after the advertised deadline will not be considered.

DSB List#14-08 Item #1, Page 11 of 11