[PDF]True Economic Impact of Project Decisions - Rackcdn.com64be6584f535e2968ea8-7b17ad3adbc87099ad3f7b89f2b60a7a.r38.cf2.rackcdn.co...
0 downloads
133 Views
2MB Size
True Economic Impact of Project Decisions Peter Kirkham and Tom Mead
Fact Or Fiction? “Upstream Developments - Speed is of the essence. The time it takes to bring a newly discovered oil or gas field into production is critical in ensuring that the project is profitable for the company. Long lead times lead to capex creep, written off over the life of the well making every barrel produced less profitable, while free cashflow is negatively impacted for longer than necessary during the development phase.” Recent E&P Financial Analyst Report
• The ‘wisdom’ that fast project schedules deliver better returns is accepted almost without question by financial analysts and business executives … but is it true? CONFIDENTIAL – UIBC 2012
2
INDEPENDENT PROJECT ANALYSIS
Measuring Change in NPV Definition of New Economic Metric Economic Gain/(Loss) : (Actual NPV – Expected NPV)
(Facilities + Drilling CAPEX)
• Metric measures change in NPV relative to total capital expenditure • Metric can be calculated for many closeout projects in current database using an economic simulator
• Provides a single metric to measure complete asset performance
NPV is “Net Present Value” and is an economic measure of a project’s value. It is calculated as the sum of discounted net cash flows over the life of a project. CONFIDENTIAL – UIBC 2012
3
INDEPENDENT PROJECT ANALYSIS
Projects With Planned Aggressive Schedules Value Appears To Be Lost, Not Gained Economic Gain/(Loss) (% of CAPEX)
50% Pr < 0.02
25%
2 * Pr < 0.02
0% (25%) (50%) (75%) (100%)
+1 Std. Dev. MEAN
(125%)
-1 Std. Dev.
(150%)
Not Schedule Aggressive
Aggressive Schedule Target
Projects with an execution schedule duration target of less than 0.85 are classified as “Aggressive Schedule Target” CONFIDENTIAL – UIBC 2012
4
INDEPENDENT PROJECT ANALYSIS
Distribution of Actual NPV Gain/(Loss) Average Project Loses Value Economic Gain/(Loss) Distribution 30% Mean = −41% Median = −31% Std. Dev. = 63%
Percentage of Projects
25%
20%
15%
10%
5%
0% (200%)
CONFIDENTIAL – UIBC 2012
(150%)
(100%)
(50%)
5
0%
50%
INDEPENDENT PROJECT ANALYSIS
Outline • The Case for Improving Decision Making •
Economic Folly of Schedule Aggression
•
Conclusions and Path Forward
CONFIDENTIAL – UIBC 2012
6
INDEPENDENT PROJECT ANALYSIS
Asset Outcomes Are Interrelated To Maximize NPV, We Must Ensure No Aspect Is Sacrificed Cost
Schedule
• Lean cost-driven development may experience quality and operability issues
• Focus on schedule leads to cost growth and poor production as corners are cut to meet startup date
Quality (Operational Performance)
• Cautious approach to asset development increases overall cost and schedule CONFIDENTIAL – UIBC 2012
7
INDEPENDENT PROJECT ANALYSIS
Ranked Drivers of NPV Gain/(Loss) Ironically the Least Important Contribution Is Schedule (40%)
(30%)
(20%)
(10%)
0%
10%
20%
30%
Initial Production
Pr > |t| 0.001
RPE Volatility
Pr > |t| 0.001
Asset Cost Growth
Pr > |t| 0.001
Execution Schedule Slip
Pr > |t| 0.005
Range reflects contribution to NPV Gain/(Loss) from P90 to P10 distribution for each outcome component CONFIDENTIAL – UIBC 2012
8
INDEPENDENT PROJECT ANALYSIS
Breakdown of Projects by Objectives Drive for Schedule Is Common 70%
60%
Percentage of Projects
50%
40%
30%
20%
10%
0% Schedule Driven Schedule Driven
CONFIDENTIAL – UIBC 2012
Cost Driven Driven Cost
9
Other Other
INDEPENDENT PROJECT ANALYSIS
Perception of Value Via Accelerated Schedule (1) Revenue
Start With an Ordinary Schedule
Baseline NPV FEL Investment FID
Capital Expenditure Time Net Revenue
Cost
Cumulative Discounted Cash Flow
CONFIDENTIAL – UIBC 2012
10
INDEPENDENT PROJECT ANALYSIS
Perception of Value Via Accelerated Schedule (2) Accelerate Time to First Oil Through Fast-Track to FID
To achieve a faster schedule, it is easier to accelerate the decision to FID than it is to accelerate execution – the “fast-track” project
Perceived NPV Gain
FID
Expectation is that capital costs and net revenue are simply shifted “to the left” and on a discounted basis, this leads to a higher NPV CONFIDENTIAL – UIBC 2012
11
INDEPENDENT PROJECT ANALYSIS
Typical Fast-Track Project Generalized Anonymous Real-Life Example • Development of fast-track offshore oil field “Rapide” • Example is intentionally obfuscated, but similar to several projects in IPA database
Facilities CAPEX Drilling CAPEX Facilities Schedule Drilling Schedule Resource Promise Estimate (MMBOE) Planned Production Plateau (KBOEPD) CONFIDENTIAL – UIBC 2012
Project Estimate at FID US$2,500 million US$1,000 million 30 months 1,000 days
Benchmark Index at FID 1.05 1.05 0.80 0.95
250
100 percent
100
100 percent
12
INDEPENDENT PROJECT ANALYSIS
Pathways To Success Appraisal and Reservoir FEL Are Reflected In All Outcomes
Facilities FEL
Appraisal
Reservoir FEL
Facilities Outcomes
Asset Outcomes
Not Integrated Asset Team
Wells FEL
Wells Outcomes
ASSET NPV CONFIDENTIAL – UIBC 2012
13
INDEPENDENT PROJECT ANALYSIS
Appraisal Affects All Subsequent Drivers Fast-Track Has Implications for All Outcomes Appraisal Effectiveness Index
Reservoir FEL
Facilities FEL
Conservative
4.00
Fair
Best Pr < 0.001
4.50
Poor
5.00
Moderate
Good
5.50 Pr < 0.001
Wells FEL
6.00 Fair
Good
Aggressive
6.50
CONFIDENTIAL – UIBC 2012
7.00
Pr < 0.001
Fair
Poor
7.50
Poor
14
INDEPENDENT PROJECT ANALYSIS
Project Definition Drives Outcomes Subsurface Definition Indicates Risk to Project Appraisal: Moderate/ Aggressive
Facilities FEL
Facilities Outcomes Facilities CI = 1.01 SI = 0.83 Outcomes Growth: −4% Slip: 3%
CA = 1.05 SA = 0.80
Reservoir FEL Fair or worse
Asset Asset Outcomes Outcomes PDA = 65%
CA = 1.05 SA = 0.95
Wells FEL
Wells Outcomes Wells CI = 2.10 SI = 1.90 Outcomes
ΔRPE = −20%
Growth: 100% Slip: 100%
Target Setting Risk
<<< Less
-----
More >>>
Results
<<< Better
-----
Worse >>>
Low
Medium
High
CA/CI = Cost Aggressiveness/Index SA/SI = Schedule Aggressiveness/Index CONFIDENTIAL – UIBC 2012
15
PDA = Production Attainment ΔRPE = Change in RPE
INDEPENDENT PROJECT ANALYSIS
Illustrated Economic Erosion (1) ‘Industry Average’ Cash Flow Stream
Industry NPV10 = US$1,991 million
CONFIDENTIAL – UIBC 2012
16
INDEPENDENT PROJECT ANALYSIS
Illustrated Economic Erosion (2) Project Initial Expected Cash Flow Stream
NPV10 = US$2,111 million
CONFIDENTIAL – UIBC 2012
17
INDEPENDENT PROJECT ANALYSIS
Illustrated Economic Erosion (3) Effect of Facilities Cost Growth and Schedule Slip
NPV10 = US$2,145 million
CONFIDENTIAL – UIBC 2012
18
INDEPENDENT PROJECT ANALYSIS
Illustrated Economic Erosion (4) Additional Effect of Production Attainment
NPV10 = US$1,059 million
CONFIDENTIAL – UIBC 2012
19
INDEPENDENT PROJECT ANALYSIS
Illustrated Economic Erosion (5) Additional Effect of Resource Promise Estimate Deviation
NPV10 = US$683 million
CONFIDENTIAL – UIBC 2012
20
INDEPENDENT PROJECT ANALYSIS
Illustrated Economic Erosion (6) Additional Effect of Wells Cost Growth and Schedule Slip
NPV10 = US$381 million
CONFIDENTIAL – UIBC 2012
21
INDEPENDENT PROJECT ANALYSIS
Misguided Tradeoffs NPV Impact From Sacrifice Outweighs Perceived Gain Common Problem: When one or more of the targets is set so aggressively that the project is likely destined to be a major disappointment
Quality is sacrificed for low cost
Safety is sacrificed for speed
Cost is sacrificed for fast schedules
Quality is sacrificed for fast schedules
CONFIDENTIAL – UIBC 2012
22
INDEPENDENT PROJECT ANALYSIS
Outline •
The Case for Improving Decision Making
• Economic Folly of Schedule Aggression •
Conclusions and Path Forward
CONFIDENTIAL – UIBC 2012
23
INDEPENDENT PROJECT ANALYSIS
Alternative Hypothesis Obsession With Schedule Erodes NPV • Roughly half of E&P projects are schedule driven and this focus is established very early in the planning phase • The emphasis on schedule limits FEL, which then has a cascading effect across all subsequent project phases • The problem is failing to recognize the magnitude of the cascading effect that these early decisions have on outcomes – Project framing does not properly account for trade-offs between cost, schedule, and operability – Leads to suboptimal NPV outcomes CONFIDENTIAL – UIBC 2012
24
INDEPENDENT PROJECT ANALYSIS
ABC of Schedule-Driven NPV Loss Schedule Focus Adversely Affects All Outcomes Antecedent
Behaviors
Consequences
Compress Definition Phase
All Outcomes Affected By Poor Definition
Schedule
Less Complete Reservoir Evaluation
Driven
Parallel Subsurface and Project Planning Poor Planning and FEL
Aggressive Schedule Targets Unrealistic Estimates
CONFIDENTIAL – UIBC 2012
25
Production Shortfall Reserve Downgrade
Cost Growth Schedule Slip
Significant Destruction of Planned NPV INDEPENDENT PROJECT ANALYSIS
Compression of FEL Driven by Business Target Date for Startup Is Often to Blame • Project teams get cornered into compressing FEL to meet business objective of early first hydrocarbons FEL Duration
Subsurface definition FEL Facilities FEL
Start FEL 2
Project execution
Target Startup
Sequential
Phased
Overlapped
CONFIDENTIAL – UIBC 2012
26
INDEPENDENT PROJECT ANALYSIS
The Economic Folly of Chasing Schedule • Chasing schedule is commonly done under the impression that NPV is enhanced
• Implicit assumption is that any negative outcomes that result from shorter appraisal and FEL duration are outweighed by the accelerated first oil date – Potential cost growth and schedule slip will have much smaller effect on NPV compared to gain from schedule – Disappointment in RPE and production attainment is rarely (if ever) considered
• Combined effect of actual cost, schedule, and production outcomes on NPV is more devastating than commonly believed – This is a non-obvious conclusion CONFIDENTIAL – UIBC 2012
30
INDEPENDENT PROJECT ANALYSIS
How to Avoid the Schedule Trap Can We Go Fast Without Eroding NPV? • Schedule itself is not the culprit for the poor economic results; practices are to blame • Schedule aggressiveness can lead to a cascading series of events that ultimately destroys NPV
Aggressive ScheduleDriven Project
CONFIDENTIAL – UIBC 2012
Compressed FEL Phase & Aggressive Appraisal
Reservoir Uncertainty & Unclear Trade-offs
31
Poor Outcomes Lead To NPV Erosion
INDEPENDENT PROJECT ANALYSIS
Breakdown of Outcomes …But Trades Fast FEL for Poor Outcomes PRODUCTION ATTAINMENT
Overlapped Schedule-Driven Sequential or Phased
0.60 0.70
FACILITY COST GROWTH
0.80 0.90
20% 15%
15%
10% 5% 0% 0.50
5%
10%
0%
0.60
5%
0.70
10%
0.80
15%
0.90
20%
FEL DURATION INDEX CONFIDENTIAL – UIBC 2012
1.00 0%
WELLS COST GROWTH 20%
SCHEDULE SLIP 33
INDEPENDENT PROJECT ANALYSIS
Recipe for Value Preservation Go Slow to Go Fast • A solid foundation of basic data and clear project objectives are the necessary starting point • Good project definition leads to a cascading series of events that ultimately preserves NPV
Completed Subsurface Definition & Clear Trade-offs
CONFIDENTIAL – UIBC 2012
Set Realistic Cost & Schedule Targets Based On Project Definition
Mitigation Of Risks During FEL Phase
35
Stable Project During Execution Preserves NPV
INDEPENDENT PROJECT ANALYSIS
Outline •
The Case for Improving Decision Making
•
Economic Folly of Schedule Aggression
• Conclusions and Path Forward
CONFIDENTIAL – UIBC 2012
39
INDEPENDENT PROJECT ANALYSIS
Fact or Fiction? “Upstream Developments - Speed is of the essence.”
Fact
Fiction
• Some projects have delivered fast schedules with no loss of NPV • A fast schedule is the result of good project definition • Faster time to first oil leads to an increase in NPV
• Chasing a fast project schedule can lead to unintended consequences • A significant proportion of NPV is eroded if the project does not meet all targets • Poorly defined projects with aggressive schedule targets have highly unpredictable NPV outcomes
CONFIDENTIAL – UIBC 2012
40
INDEPENDENT PROJECT ANALYSIS
Emphasise FEL, Not Schedule The Tail Cannot Wag the Dog • Good practices lead to successful economic outcomes irrespective of whether or not a project is schedule driven • The prize for well-defined projects is competitive targets and preservation of expected NPV • Achieving Best Practical project definition requires both time and effort; neither are made reliably available to schedule-driven projects by business
The most challenging aspect of delivering a successful schedule-driven project is NOT focusing on the schedule CONFIDENTIAL – UIBC 2012
41
INDEPENDENT PROJECT ANALYSIS
Good FEL Preserves Economic Value • It is possible to achieve a successful schedule-driven project with an aggressive schedule target • Well-defined projects with good integrated schedule and comprehensive project execution planning are the differentiator for success • Poorly planned projects suffer larger NPV loss on average, but are also more unpredictable
Without Good or better FEL, a project is potentially giving up over half of its NPV
CONFIDENTIAL – UIBC 2012
42
INDEPENDENT PROJECT ANALYSIS
Making Good Decisions Is a Complex Optimisation Problem • There is a complex relationship between project outcomes and project drivers • An economic simulator backed by strong data relating drivers to outcomes is needed to reveal to true effect of project decisions – Provides insight into the most appropriate balance between cost, schedule, and production attainment – Indicates the possible unintended consequences of any particular decision
The true economic impact of a project decision is non-obvious and can lead to unintended consequences CONFIDENTIAL – UIBC 2012
43
INDEPENDENT PROJECT ANALYSIS
Thank You!