November 2015

Western Ticket Hall Update Duration of work

Ventilation Shaft CSJV are scheduled to continue the enabling works with a consented extension to working hours on Saturday 28 and Sunday 29 November. From Monday 30 November the site will be operational on a 24 hour basis. The construction of the ventilation shaft will be completed using the slip form method. Slip forming is a construction method in which concrete is poured into a continuously moving form. The vertical concrete form will be surrounded by 3 working platforms from which workers fix the reinforcement, pour concrete and install all the cast in items. Together, the concrete form and working platforms are raised by means of hydraulic jacks. The jacks climb on smooth rods or structural tubing embedded in the hardened concrete. Reinforcement is fixed just ahead of the form, which is then filled in layers with concrete. A mobile self erecting crane will be operational during the slip form construction works located on Gilbert Street. Platform Concrete will be delivered via Davies Street and will be parked on Weighhouse Street.

• CSJV has been working 08:00 to 20:00 Monday to Friday and 08:00 to 16:00 on Saturdays • On Saturday 28 November working hours will be 08:00 to 18:00 • On Sunday 29 November working hours will be 09:00 to 18:00 • From 30 November CSJV will be working 24/7 to complete the vent shaft

What to expect

Ventilation Shaft

• Deliveries for concrete pours • 24/7 working on site • General site activity

Track bed

What we will do • Monitor dust, noise and vibration to keep it within permitted levels

Grout Shafts Both grout shafts located on South Molton Lane and Davies Mews have now been decommissioned. South Molton Lane will remain as pedestrian access only until further notice. Davies Mews is open to both motorists and pedestrians. From Monday 30th November we are consented by Westminster City Council to work 24 hours a day for a 12 day period to complete the ventilation shaft.

C412-XRL-Z1-XBU-C125_1-50002

• Traffic marshalls on site to help with traffic flow and vehicle access into and out of the site.

About Crossrail Crossrail is Europe’s largest construction project, delivering a new railway for London and the South East. When the service opens Crossrail trains will travel from Reading and Heathrow in the west to Shenfield and Abbey Wood in the east via new twin tunnels under central London. It will link Heathrow Airport, the West End, the City of London and Canary Wharf.

Bond Street Community Liaison Panel Crossrail runs a community liaison panel for each central London station to keep local community representatives informed of progress and plans. If you would like further information please contact [email protected]